10/06/2026
Progress continues across the BAQUS Les Ozouets project, with key works advancing across the main building, construction building, PAC building and wider external areas.
Within the main building, fire protection boarding is ongoing across the ground, first and second floors, alongside continued SFS installation, external boarding, sealing works and the installation of parapet framing to the level 3 roof. Window installation and glazing have also progressed on the north elevation, while the final roof coating to level 3 is now approximately 90% complete.
Additional progress includes preparation works to the second-floor dwarf wall, fire stopping sample walls being erected, and the first sections of external supports for cladding now being installed.
Across the wider site, scaffolding, fall arrest, mezzanine deck works, Sika waterproofing, retaining walls, roadway preparation and motorcycle bay works are all progressing, supporting the continued delivery of this important education and community-focused development.